Below is a list of projects we will be working on during that week. Unfortunately, it is not feasible to install a cold plunge tub as the cost range for that is between $10,000 and $20,000 and we do not have the money. We also have plans to install a drinking fountain outside next to the hot tub. The drinking fountain needs to ADA accessible, frost free (as it will be outside) and up to all current codes.
-
Bathhouse Projects 2010:
Install drinking fountain
Change out drain covers to comply with federal regulations
Change out sand in sand filters
Install towel chute between shoe changing area and changing room
Repair shower shelf
Repair ceiling and wall from water damage
Stain courtyard walls
Relocate pool sweeper
Stain shower screen
Touch up paint in bathhouse
Repair bathhouse restroom doors
Repair courtyard door
Clean under courtyard deck and address drainage issue
Change pumphouse/massage hall door
Add sound absorbers to pump house
Build wood frame around pool rules
Solve the shower stub solution